Northern NSW - WWTP Lagoon Desludging

Sth Lismore 5.JPG
Sth Lismore 3.JPG

Projects > Municipal > Northern NSW - WWTP Desluding - Lagoons

January, 2019

Situation:

This Northern NSW WWTP site was undergoing a major upgrade and a major element of this project was that two sludge lagoons needed to be dewatered to provide space for a future solar farm.

Our Approach:

650  dry tonnes of sludge was removed using our DINO 6 auger suction dredge and dewatered via our VITONE V9 centrifuge. The material was subsequently transported to the designated stockpile on site for further consolidation (pictured).

Result:

The two lagoons were comprehensively desludged and back filling was then performed on Lagoon One to allow for re-purposing. Dredging Solutions were  subsequently engaged  to assist with removal of sludge from the digesters on site during the same upgrades.